Do you want to update your ABC project with new data from your ERP system? .. Then continue reading. If you have made changes to the structure of your data, for instance added a new column or changed the date format, go to this guide
Update an existing project with new data
- Open the existing project (.abcx)
- Choose "Current project / Update project / Change data file" --> navigate to the newest data file
- If your data file is named the same as last time and is located in the same folder (i.e. your IT department overwrites the raw data file every month), choose the option at the top: "Update from data file"
Now the project file is updated.
Remember to save before closing, otherwise, the project will display the old data the next time you open it.